Which of the following are controlled by the materials planner?
A) exception messages
B) released orders
C) planned orders
D) firm planned orders
E) all of the above
D
You might also like to view...
Tata Motors assembles cars from their own parts and subassemblies and also controls the mining and fabrication of the materials used to create those parts
When Anand ordered his luxury sedan with the platinum dashboard he knew he wouldn't be taking delivery of his dream car the next week. Rather, he would be waiting a while thanks to: A) a mismatch between supply chain lead time and customer demand. B) a mismatch between overall demand levels and productive capacity. C) a mismatch between demand and the most efficient production volume. D) a mismatch between demand and the most efficient shipment volume.
A(n) __________ records the assignment of storage locations to files
Fill in the blank(s) with correct word