If the NPV (Net Present Value) of a project with multiple sign reversals is positive, then the
project's required rate of return ________ its calculated IRR (Internal Rate of Return).
A) must be greater than
B) must be less than
C) could be greater or less than
D) The required rate of return cannot be determined without actual cash flows.
C