What is the early start time for Activity G given the activity times and precedence requirements shown in the table?

Activity Time Predecessor
A 5 --
B 7 --
C 8 A
D 7 A
E 4 B
F 8 C, D
G 9 E, F
H 7 G

A) 22
B) 21
C) 20
D) 19

B