A project being analyzed by PERT has 38 activities, 16 of which are on the critical path

If the estimated time along the critical path is 90 days with a project variance of 25, what is the probability that the project will be completed in 88 days or less?
A) 0.0228
B) 0.3446
C) 0.6554
D) 0.9772
E) 18

B