As a rule of thumb estimate, what percentage of the entire development effort should be devoted to the project initiation and planning process?
A) Between 10 and 20 percent
B) Less than 5 percent
C) Less than 10 percent
D) Between 20 and 30 percent
E) Over 50 percent
A
Explanation: A) In other words, you should not be reluctant to spend considerable time and energy early in the project's life in order to fully understand the motivation for the requested system.
CL
You might also like to view...
A researcher is interested in establishing emic validity of her findings. In order to do so, she must show that:
a. similar results have been reported by others working independently on the problem. b. similar results can be obtained if the study were to be repeated. c. key members of the group included in her study agreed with the findings of her study. d. the findings of her study are generalizable. e. the research methodology of her study complies with the necessary research standards
Broker Kenneth arrives to present a purchase offer to Dorita, an invalid, and finds her son and his wife also present. In the presence of Broker Kenneth, both individuals persistently urge Dorita to accept the offer, even though it is much lower than the price she has been asking for her home. If Dorita accepts the offer, she may later claim that
A) Kenneth should not have brought her such a low offer for her property. B) she was under duress from her son and daughter-in-law, and therefore, the contract is voidable. C) Kenneth defrauded her by allowing her son and his wife to see the purchase offer he brought to her. D) her consumer protection rights have been usurped by her son and daughter-in-law.