Metro City would like a pedestrian bridge constructed across Big Creek. The city will accept bids on the project until a specified date
Bidders must submit a bid bond that guarantees if the bid is accepted, the bidder will sign the construction contract and furnish a bond that guarantees the construction work will be completed according to contract specifications. This second bond the bidder must post is a
A) performance bond.
B) payment bond.
C) maintenance bond.
D) completion bond.
Answer: A
You might also like to view...
If the key variables have not been defined or are defined in a manner inconsistent with the researcher's definition, then the usefulness of the data is limited. This statement refers to the ________ criteria for evaluating secondary data
A) nature B) objective C) error/accuracy D) currency
The income statement shows gross profit, which is equal to
A) net sales minus cost of goods sold. B) earnings before taxes minus taxes. C) operating income minus interest. D) operating income minus operating expenses. E) gross revenues minus returns and allowances.