Project monitoring, an activity of a project manager, _____.?
A. requires guiding, supervising, and coordinating a project team's workload
B. ?involves the creation of a specific timetable, usually in the form of charts that show tasks, task dependencies, and critical tasks that might delay a project
C. ?consists of staffing, which includes selecting the project team and assigning specific tasks to team members
D. ?includes identifying and arranging project tasks and estimating completion times and costs
Answer: A