Post implementation review is conducted to
A) determine whether a new system meets its planned objectives.
B) determine how well the project team performed in developing the new system.
C) prioritize future modifications to the system.
D) provide external auditors assurance that a new system has been placed into service.
Answer: A
Business
You might also like to view...
The number of units added to inventory depends on _____________
Fill in the blank(s) with the appropriate word(s).
Business
Consider a capital budgeting example with five projects from which to select. Let xi = 1 if project a is selected, 0 if not, for i = 1, 2, 3, 4, 5
Write the appropriate constraint(s) for the following condition: If project 1 is chosen, project 5 must not be chosen.