A project is composed of the twelve activities shown in the table. What are the earliest and latest start times for each of these activities?

Activity Time (days) Predecessors
A 3 --
B 3 A
C 15 A
D 2 B
E 12 B
F 16 C
G 2 C
H 11 E, F
I 9 D, G
J 6 D, E
K 15 H, I
L 13 J, K
What will be an ideal response?

Answer:
Activity ES LS
A 0 0
B 3 19
C 3 3
D 6 34
E 6 22
F 18 18
G 18 34
H 34 34
I 20 36
J 18 54
K 45 45
L 60 60