Each X requires 2 of component Y and 1 of part W. Each Y requires 10 of Z. Each W requires 3 of Q and 2 of R. Lead times are X = 1 week, Y = 1 week, W = 2 weeks, R = 1 week, Z = 3 weeks, and Q = 3 weeks. Construct the time-phased product structure

What will be an ideal response?

Solution: