If the project sponsor never gives the project manager authority to make decisions and the project fails, which reason for failure below does this illustrate?

A. Problems with communications
B. Problems with project deliverables
C. Problems with the project process
D. Problems with unforeseeable circumstances

C. Problems with the project process