A seven activity project has the activity durations (in weeks) and costs shown in the table. In addition to the activity costs shown in the table, there is an additional daily fixed cost of $450. What is the least expensive project completion cost?

Activity
Predecessor Normal Duration
Normal Cost Crash Duration
Crash Cost
A -- 7 $2000 5 $3000
B -- 8 $1500 6 $2000
C A 12 $2500 10 $2900
D B 13 $3000 10 $4200
E B 15 $4000 12 $5500
F C, E 10 $3200 8 $4000
G D 7 $1800 6 $2200

A) $31,450
B) $31,900
C) $32,350
D) $32,700

Answer: C

Business

You might also like to view...

An auditor's evaluation of the reasonableness of a company's loan loss reserve would normally be made during which phase of the audit?

A) Gaining an understanding of the auditee's industry. B) Client acceptance. C) Consideration of internal control systems. D) Auditing business processes and related accounts.

Business

________ is the level of consistency of a research measurement

A) Flexibility B) Validity C) Responsiveness D) Reliability E) Representativeness

Business