The earliest start time for an activity is
a. the date that all the resources for the project are available.
b. calculated using the project start time and the estimated duration of all of its preceding activities.
c. cannot be earlier than estimated, even if some activities are accelerated.
d. should not be delayed or would cause the project to be delayed.
b