Use Johnson's rule to determine the optimal sequencing for the five jobs to be processed on two machines in a fixed order (Machine 1 before Machine 2). The processing times in hours are given in the table below

a. What is the optimal sequence?
b.

What is the total flow time for this sequence?

Job Machine 1 Machine 2
A 10 11
B 8 17
C 14 10
D 13 7
E 10 8
F 25 9
G 6 15

(a, b) The optimal sequence is G-B-A-C-F-E-D, and the total flow time is 93 hours, as shown in the software solution below.

Business

You might also like to view...

An example of an economic trading-area barrier is _____

a. travel distance b. travel time c. high sales-tax rates d. travel difficulty as measured by road conditions

Business

An expatriate manager refers to:

A. a citizen of one country who is working abroad in one of the firm's subsidiaries. B. a parent-country national who works in the parent country. C. a host-country national who works in the host country. D. any person who lives in a foreign country. E. a person willing to work in different departments of a foreign firm.

Business