A project manager analyzed the quality of risk data and asked various stakeholders to determine the probability and impact of a number of risks. He is about to move to the next process of risk management. Based on this information, what has the project manager forgotton to do?
A. Create a fallback plan.
B. Provide a standardized risk rating matrix.
C. Evaluate trends in risk analysis.
D. Identify triggers.
Ans: B. Provide a standardized risk rating matrix.