Determine which activities should be crashed to shorten the project by 3 days. What is the cost?

What will be an ideal response?

Answer: Crash C by 1 day, E by 1 day, and then B by 1 day and E by an additional day. Total cost = $1400.

Crash schedule:

Path Normal time Crash C Crash E Crash B & E
ABF 18 18 18 17
CEDF 20 19 18 17
Cost: $300 $500 $600