Which of the following is NOT true about using Project 2013?

A) Project 2013 should not be the decision-making authority on a project plan.
B) Project plans in Project 2013 are created by setting critical paths.
C) Project 2013 can provide project managers with an orderly way of creating a project schedule.
D) Project managers should not rely on the software to make all the scheduling decisions for a project.

B

Computer Science & Information Technology

You might also like to view...

The result of =ROUNDUP(123.456,0 ) is ________

Fill in the blank(s) with correct word

Computer Science & Information Technology

A worksheet is a collection of workbooks.

Answer the following statement true (T) or false (F)

Computer Science & Information Technology