Which of the following is NOT true about using Project 2013?
A) Project 2013 should not be the decision-making authority on a project plan.
B) Project plans in Project 2013 are created by setting critical paths.
C) Project 2013 can provide project managers with an orderly way of creating a project schedule.
D) Project managers should not rely on the software to make all the scheduling decisions for a project.
B