The table shows a master schedule for end item Z that is produced according to the product structure tree shown below. Beginning inventories and lead times for components of Z are given in the table

The lot sizes for A, B, and C are 100 units. Complete a materials requirement plan for components A, B, and C.

Period 1 2 3 4 5 6
MPS Qty 0 0 0 250 275 275

Component A B C D E
Lead Time 1 2 2 2 1
Beginning Inv 50 75 100 15 40

What will be an ideal response?

Answer:
Week 1 2 3 4 5 6
Z 0 0 0 250 275 275

Week 1 2 3 4 5 6
E
Gross 500 550 550
Sched Rec 0 0 0
End Inv 40 40 40 0 0 0
Net Req 460 550 550
Plan Rec 460 550 550
Plan Ord 460 550 550

Week 1 2 3 4 5 6
A
Gross 920 1850 1925 825
Sched Rec
End Inv 50 50 30 80 55 30
Net Req 870 1820 1845 770
Plan Rec 900 1900 1900 800
Plan Ord 900 1900 1900 800

Week 1 2 3 4 5 6
B 920 1100 1100
Gross 920 1100 1100
Sched Rec
End Inv 75 75 55 55 55
Net Req 845 1045 1045
Plan Rec 900 1100 1100
Plan Ord 900 1100 1100

Week 1 2 3 4 5 6
C
Gross 1380 1650 1650
Sched Rec
End Inv 100 100 20 70 20
Net Req 1280 1630 1580
Plan Rec 1300 1700 1600
Plan Ord 1300 1700 1600

Business

You might also like to view...

Only managers within an organization need to be aware that the similar-to-me bias might predispose them to help members who are similar to them

Indicate whether the statement is true or false

Business

When a company has earned a net income, the net income amount is entered on the work sheet on the

a. credit side of the Income Statement columns and the debit side of the Balance Sheet columns. b. debit side of both the Income Statement and the Balance Sheet columns. c. debit side of the Income Statement columns and the credit side of the Balance Sheet columns. d. credit side of both the Income Statement and the Balance Sheet columns.

Business