The seventh unit of production took 63.423 minutes while the ninth unit of production took 59.8 minutes. What is the improvement rate?

What will be an ideal response?

T1. = 63.423/(7^b) = 59.8/(9^b)
b = -.234
-.234 = log (1-IR)/log 2.
Log (1-IR) = -.070441
IR = 15%
Note: Students may also recognize this b value from Table E.2 as an 85% learning curve and then convert that into an improvement rate.

Business

You might also like to view...

Which of the following is not typically a characteristic of commercial paper borrowing?

A) banks are not the lenders B) borrowers have high credit quality C) the loans are secured. D) maturity is short-term

Business

What is known as a Storage location?

a. The place where raw materials are received b. The place within a plant where materials are kept until they are needed c. The place where materials are collected for staging and inspection d. The place within a plant where machines are installed for production purposes e. The place within a plant where finished goods are kept for sale

Business