Five jobs are waiting to be processed. Their processing times and due dates are given below
Using the earliest due date dispatching rule, in which order should the jobs be processed?
Job Processing Time (days) Job due date (days)
A 4 7
B 2 4
C 8 11
D 3 5
E 5 8
A) C, E, A, D, B
B) A, B, C, D, E
C) B, D, A, E, C
D) C, B, A, E, D
E) B, D, A, C, E
C