Managers use the network analysis of PERT and CPM to help them

A) derive flexibility by identifying noncritical activities.
B) replan, reschedule, and reallocate resources such as manpower and finances.
C) plan, schedule, monitor, and control large and complex projects.
D) All of the above
E) None of the above

D