A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table. Use Goldratt's model to determine the aggregated buffer for this project
Activity Average Worst-Case
A 10 20
B 15 25
C 20 30
D 25 35
A) 20 days
B) 10 days
C) 15 days
D) 5 days
A