What is the early finish time for activity K?

Project Sand Mandala
Carrie meticulously calculated the early and late start and finish times for her latest project and recorded them using different colors of sand on a pristine slab of white marble. She used red for late start and late finish times and green for early start and early finish times. Activity durations and their identifiers were written with black sand. She finished her task and had an opportunity to admire her work only briefly before a colleague came by and swept most of it away. Sadly, this was before Carrie could record the numbers on a more permanent medium, so now she turns to you to help.

Activity Predecessor Duration Early Start Early Finish Late Start Late Finish
A - 10
B - 7 11
C A 7
D A 15 14
E B 11 19
F B 10
G D,E 24
H F 24
J C 28
K G,H,J 36

A) 36
B) 35
C) 34
D) 33

Answer: A

Business

You might also like to view...

Each of the following is an example of an em inducement EXCEPT which one?

A. Career or job opportunities B. Pay and benefits C. Job security D. Social Security benefits

Business

Suppose a U.S. importer purchases an Italian product today but will not pay for it for 90 days. The

cost of the product today is 30,000 euros. The spot exchange rate today is .6233 euros per dollar. If the U.S. importer does not hedge the position, which of the following spot exchange rates in 90 days will yield the highest returns? A) $1.4844 per euro B) 0.6833 euros per dollar C) $1.5387 per euro D) 0.6499 euros per dollar

Business