Crashing a schedule is reducing a project completion time by ___________________.

a) renegotiating with management
b) realign tasks in parallel
c) rearranging all tasks
d) throwing additional resources to the critical path
e) throwing less resources to the critical path

d) throwing additional resources to the critical path