Consider the project summarized in Table 11-8. Suppose in addition to the costs shown in the table, the mad scientist faces a $2,000 per week opportunity cost of not being in control of the world. Which of these activities should not be reduced in an effort to deliver a minimum cost (both project and opportunity cost) project?
A) F
B) H
C) G
D) E