Why is using multiple predetermined overhead allocation rates more accurate than using a single plantwide allocation rate?
What will be an ideal response
The allocation process is the same, except there are multiple cost pools and multiple allocation bases. Having more than one allocation rate more accurately reflects the way products actually use a company's resources.