PERT diagrams are bar charts that show production managers what projects are being worked on and what stage they are in
Indicate whether the statement is true or false.
Answer: FALSE
Explanation: PERT helps managers identify the optimal sequencing of activities, the expected time for project completion, and the best use of resources. PERT is not a bar chart.
You might also like to view...
The US Treasury received $1 trillion in tax payments. It spent $850 billion on "current" goods and services plus transfer payments and interest on existing bonds. It spent $200 billion on capital projects (such as highways and medical research). Which of the following is correct?
a) It has a surplus of $150 billion but must issue $50 billion in new bonds b) It has a deficit of $50 billion and must issue $50 billion in new bonds c) It has a deficit of $50 billion and must issue $150 billion in new bonds d) It has a surplus of $150 billion and can pay off $150 billion in existing bonds
All of the following are mentioned in the text as specific objectives of a questionnaire EXCEPT:
A) translate the researcher's information needs into a set of specific questions that respondents are willing and able to answer. B) minimize demands imposed on respondents. C) minimize response error. D) collect demographic information that can be used in later direct mail campaigns. E) B and D