A project is currently scheduled to be finished on its normal earliest completion date. The project manager has the opportunity to earn a bonus if the project can be completed three weeks ahead of schedule

The increase in project direct costs related to crashing activities would be $40,000. Also, project indirect costs are $15,000 per week. What is the smallest bonus that the project manager should accept if he or she wants to avoid increasing overall project costs?
A) less than or equal to $5,000
B) greater than $5000 but less than or equal to $10,000
C) greater than $10,000 but less than or equal to $15,000
D) greater than $15,000

A

Business

You might also like to view...

The industry average receivables collection period:

Mary Gonzales is evaluating companies in the office supply industry and has compiled the following information: 20X1 20X2 Company Credit Sales ($) Average Receivables Balance ($) Credit Sales ($) Average Receivables Balance ($) A 5.0 million 1.0 million 6.0 million 1.2 million B 3.0 million 1.2 million 4.0 million 1.5 million C 2.5 million 0.8 million 3.0 million 1.0 million D 0.5 million 0.1 million 0.6 million 0.2 million Industry 25.0 million 5.0 million 28.0 million 5.4 million A. increased from 20X1 to 20X2. B. decreased from 20X1 to 20X2. C. did not change from 20X1 to 20X2.

Business

The marketing concept philosophy emphasizes the need to have a:

A) price advantage. B) unique product. C) sustainable strategy. D) customer focus.

Business