Concrete delivered to a construction site costs $250 a cubic yard. What is the cost of the concrete needed to build a 6-inch-thick patio slab 20 feet by 10 feet?

Additional information:
The volume of a rectangular slab is the product of its three dimensions. The 6 inches thickness of the slab is 1/2 foot thick

Preliminary calculations
Compute the volume in cu ft for the entire job 20 (ft) * 10 (ft) * 1/2 (ft) = 100 (cu ft) Since this is the entire job
100 (cu ft /job)
Note: An alternative approach would be to include the volume calculation in
the equation below. However, doing it as a preliminary calculation seems more straight forward.

Let x equal what you are trying to find
x = ($ / job) Note: Made up unit "job" form above.
Reciprocal Factors
250 ($ / cu yd) 1 / 250 (cu yd / $)
27 (cu ft / cu yd) 1 / 27 (cu yd / cu ft)
Build an equation
x ($ / job) = 250 ($/cu yd) * 1 / 27 (cu yd / cu ft) * 100 (cu ft / job)
Multiply factors
x ($ / job) = 925.93 ($ / job) Cost of concrete is $925.93.

Computer Science & Information Technology

You might also like to view...

By default, which of the following fields would be listed in the fields sidebar under interesting Fields?

A. host B. index C. source D. sourcetype

Computer Science & Information Technology

A(n) ____ loop is one that never ends.

A. broken B. infinite C. variable-condition D. fixed-count

Computer Science & Information Technology