Determine the estimated completion time of the project

A) 23 days
B) 22 days
C) 25 days
D) 20 days

Consider the following project.

Activity Immediate Processor Activity Time (days)
A - 6
B - 8
C A, B 5
D B 4
E C 7
F C, D 3
G D 6
H E, F, G 5

Answer: C