Because Riley and her project team were skilled at marketing but not photography, Riley contracted a photographer to take pictures of menu items for a marketing campaign she and her team were doing for a local restaurant. If the photographer was already booked for the dates Riley requested, causing Riley to push back the pictures two weeks, which two items below were NOT impacted in the project plan?

A. Project schedule
B. Project budget
C. Resource plan
D. Risk management plan
E. Communication plan

D. Risk management plan