A partially solved PERT problem is detailed in the table below. Times are given in weeks

Activity Preceding Optimistic
Time Probable
Time Pessimistic
Time Expected
Time Variance
A -- 7 9 14 1.361
B A 2 2 8 0
C A 8 12 16 0
D A 3 5 10 1.361
E B 4 6 8 0
F B 6 8 10 0
G C, F 2 3 4 0
H D 2 2 8 1.000
I H 6 8 16 2.778
J G, I 4 6 14 2.778
K E, J 2 2 5 0.250

a. Calculate the expected time for each activity. Enter these values in the appropriate column in the table above.
b. Which activities form the critical path?
c. What is the estimated time of the critical path?
d. What are the project variance and the project standard deviation?
e. What is the probability of completion of the project after week 40?

(a) A=9.5 B=3 C=12 D=5.5 E=6 F=8 G=3 H=3 I=9 J=7 K=2.5
(b) A-D-H-I-J-K; (c) 36.5; (d) 9.53, 3.09; (e) 0.13

Business

You might also like to view...

Equity securities in which the investor owns less than 20% ownership in the voting stock of the investee can be ________

A) significant interest investments B) controlling interest investments C) held-to-maturity investments D) either trading investments or available-for-sale investments

Business

The major outcome of a business agreement based on reciprocity is a mutual exchange of benefits

Indicate whether the statement is true or false

Business