What is the NPV for a project if its cost of capital is 12 percent and its initial after-tax cost is $5,000,000 and it is expected to provide after-tax operating cash flows of $1,800,000 in year 1,

$1,900,000 in year 2, $1,700,000 in year 3, and ($1,300,000 ) in year 4?
A) -$1,494,336
B) $158,011
C) -$158,011
D) $3,505,664