The second step in Theory of Constraints application, "exploit the bottleneck(s)," means that the analyst should:
A) create a schedule that maximizes the throughput of the bottlenecks.
B) repeat the analysis process to look for other bottlenecks.
C) consider increasing capacity of the bottleneck.
D) schedule non-bottleneck resources to support the bottleneck.
A