In a network diagram, an activity:
A) is the largest unit of work effort consuming both time and resources that a project manager can schedule and control.
B) is the smallest unit of work effort consuming both time and resources that a project manager can schedule and control.
C) should always be something the company has had experience with.
D) must always have a single, precise estimate for the time duration.
B