The overall project risk factor is known to be 0.6. The probability of dependency failure is twice the probability of complexity failure and four times the probability of maturity failure

The consequence of performance failure is twice the consequence of reliability failure, four times the consequence of schedule failure and eight times the consequence of cost failure. What is the probability of maturity failure?

Maturity X Cost Y
Complexity 2X Schedule 2Y
Dependency 4X Reliability 4Y
Performance 8Y
A) 0.213
B) 0.197
C) 0.104
D) 0.148

D