If a project in Project 2013 is set to ________, the project schedule is calculated based on the project's calendar, project tasks and task durations, task dependencies, resource assignments, and any constraint dates assigned to tasks
A) Auto Scheduled B) Duration
C) Scheduling Engine D) Manually Scheduled
A