Jennings Company manufactures ceiling fans and uses an activity-based costing system
Each ceiling fan has 20 separate parts. The direct materials cost is $85 and each ceiling fan requires 2.50 hours of machine time to manufacture. Additional information is as follows:
Activity Allocation Base Predetermined Overhead Allocation Rate
Materials handling Number of parts $ 0.04
Machining Machine hours 7.60
Assembling Number of parts 0.40
Packaging Number of finished units 3.90
What is the total manufacturing cost per ceiling fan? (Round any intermediate calculations and your final answer to the nearest cent.)
A) $97.70
B) $104.80
C) $112.80
D) $116.70
D .D)
Calculation of total manufacturing cost per ceiling fan:
Direct materials $85.00
Materials handling cost per unit ($0.04 x 20 ) 0.80
Machining cost per unit ($7.60 x $2.50 ) 19.00
Cost of assembling per fan ($0.40 x 20 ) 8.00
Packaging 3.90
Total manufacturing cost per ceiling fan $116.70
You might also like to view...
The IRS is entitled to choose a place and time for an audit, without regard to the inconvenience to the taxpayer or the reasonableness of the request
a. true b. false
Which of the following was a major U.S. tax incentive for exporters that the WTO recently ruled was an illegal subsidy?
A) NTR B) CVD C) FSC D) NTB E) HTS