This resource loading table shows the requirements for a five-task project that has a 42-day duration. The table is designed to reflect an early start schedule. Activity D has only one predecessor and activities C and E have two each

What differences exist between this table and the late start resource table?

The late start table is below. The AC path has slack, so differences arise from the starting times for these activities. Activity A has almost as much slack 8. as its duration 10. as is the case for activity C (duration of 8 and slack of 6). Activity A needs 10 units of resources and C needs 15 units per period, so these resources can be shifted almost the entire duration of either (or both) activities.

Business

You might also like to view...

On March 5, a prospective buyer gave a broker his personal check for $1,000 payable to the seller along with an offer to buy the property. He told the broker that the check should not be cashed until March 30. Which of the following is correct?

A: The broker should refuse to accept the check as a deposit; B: The broker should not hold the check until March 30th, but should cash it immediately; C: The broker must deliver the check to the seller or to escrow within one business day; D: The broker may hold the check, but must tell the seller that it is being held uncashed before the seller accepts the offer.

Business

Which of the following situations causes communication problems within an organization that uses functional structure?

A) the organization uses the system of management by objectives B) the organization operates in a stable environment C) the organization operates in a rich environment D) the organization develops more functions that are increasingly distant from one another

Business