A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table

What is the length of the project buffer if this project is managed using critical chain methodology?

Activity Predecessor Length Activity Predecessor Length
A -- 20 D B 16
B A 20 E C 8
C A 10 F D, E 8
A) 4.5
B) 11.5
C) 20.5
D) 16

D

Business

You might also like to view...

Providing a current date that identifies when the form or report was generated corresponds to the form and report guideline of:

A) balance the layout. B) design an easy navigation system. C) include meaningful information. D) use meaningful titles. E) market the form.

Business

Which of the following is a cost associated with product platforms?

a. products created off a product platform are more distinctive b. need less cross-functional coordination c. lower-level products have to be over designed so they can share systems and components with higher-level prices d. all of the above are costs associated with product platforms

Business