A project manager is using a simple scoring model to decide which of four projects is best, given the company's limited resources. The criteria, importance weights, and scores for each are shown in the table
Which project should be chosen?
Project Criteria Importance Weight Score
1 1 3
Greenlight 2 2 2
3 3 1
1 1 2
Runway 2 2 1
3 3 3
1 1 1
X 2 2 2
3 3 2
1 1 2
Ilevomit 2 2 2
3 3 2
A) Project Greenlight
B) Project Runway
C) Project X
D) Project Ilevomit
B