How busy are the servers on average?

At Joe's Pool Hall they rent tables by the hour and also rent Balabushka pool cues for purists that can't afford their own. The rental process for these cues is exhaustive and takes an hour and a half for each application. There are three leasing agents that conduct these interviews, and on average, it is one hour between customer arrivals.

A) 50% utilized
B) 60% utilized
C) 70% utilized
D) 80% utilized

Answer: A

Business

You might also like to view...

Under the Secured Transactions Article of the UCC, for which of the following types of collateral must a financing statement be filed in order to perfect a purchase money security interest?

A. Stock certificates. B. Promissory notes. C. Personal jewelry. D. Inventory.

Business

The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day. Which activity could be split to help the project team finish on time and meet the resource cap?

A) Activity A B) Activities B and C C) Activities D and E D) Activity E and F