Use the information in the table to determine the late start time for Activity E

Task Predecessor Duration Early Start Early Finish Late Start Late Finish
A -- 8
B A 14
C A 23 8
D C, B 6 23 26
E C 32
F D, E 32 38
A) Day 23
B) Day 26
C) Day 32
D) Day 17

A