Picture yourself as a project manager intent on bringing CCPM to your organization that has historically used classic critical path project management
How would you convince your project team to develop 50% estimates for their project contributions rather than the 90% estimates they have used since they started with the company?
This will require a culture change for all project participants. The idea is that the project must work in a "no blame" environment and that all parties agree that it is literally a coin flip as to whether their piece of the project meets a 50% estimate. Answers will vary as to how to bring about the culture change. Some students may cite a need to manage a couple of projects this way before team members accept the new mindset. Training exercises, such as the Deming Red Bead experiment, might be used as a lesson, albeit as a counterexample. The project manager may take the estimates provided by the project team as given, then run a parallel analysis using the CCPM approach, to show the team after the fact, how things would have worked out — or — hold his team to their estimates but report to his superiors a CCPM schedule.
You might also like to view...
Elite Services, Inc. pays $1,350,000 to acquire 38% of voting stock of Grey Investments, Inc. on March 5, 2017. Which of the following is the correct journal entry for the transaction?
A) Long-term Investments-Grey Investments, Inc. 1,350,000 Cash 1,350,000 B) Long-term Investments-Available-for-Sale 1,350,000 Cash 1,350,000 C) Cash 1,350,000 Long-term Investments-Available-for-Sale 1,350,000 D) Cash 1,350,000 Long-term Investments-Grey Investments, Inc. 1,350,000
If the USD is selling at a discount relative to the yen in the forward market, is the forward price of JPY/USD larger or smaller that the spot price of the JPY/USD?
A) larger B) smaller C) indeterminate D) the same