Consider the network described in the table below

Activity Immediate
Predecessor(s) Pessimistic Probable Optimistic
J -- 15 10 8
K -- 9 8 7
L J 10 6 5
M J 3 3 3
N K,M 9 5 1
O K,M 10 7 4
P L,N 10 8 3

a. Calculate the expected duration of each activity.
b. Calculate the expected duration and variance of the critical path.
c. Calculate the probability that the project will be completed in fewer than 30 time units.

(a) See table below. (b) Tasks J-M-N-P are critical. The sum of their expected durations is 26.00; the sum of their variances is 4.50. (c) The standard deviation along the path is = 2.12; the probability that Duration < 30 is the probability that z < (30 - 26.00)/2.12 = 1.89. The associated normal curve area is 0.97062.

Task Early Start Early Finish Late Start Late Finish Slack Mean Variance
J 0 10.5 0 10.5 0 10.5 1.361111
K 0 8 5.5 13.5 5.5 8
L 10.5 17 19.5 26 9 6.5
M 10.5 13.5 10.5 13.5 0 3 0
N 13.5 18.5 13.5 18.5 0 5 1.777778
O 13.5 20.5 19 26 5.5 7
P 18.5 26 18.5 26 0 7.5 1.361111
Project 26 Project 4.5
Std.dev 2.12132

Business

You might also like to view...

Which of the following types of tenancies are usually created by express agreement?

A) Tenancy at sufferance and tenancy at will B) Periodic tenancy and tenancy at sufferance C) Tenancy for years and periodic tenancy D) Periodic tenancy and tenancy at will E) Tenancy for years and tenancy at will

Business

What is the IRR for a project with a current cost of $7,000 that is expected to produce cash inflows of $1,000 at the end of each of the next 10 years? Round answer to the nearest whole percent

A) 10% B) 8% C) 7% D) 11% E) 6%

Business