Slack time in a network is the

A) amount of time that an activity would take assuming very unfavorable conditions.
B) shortest amount of time that could be required to complete the activity.
C) amount of time that you would expect it would take to complete the activity.
D) difference between the expected completion time of the project using pessimistic times and the expected completion time of the project using optimistic times.
E) amount of time that an activity can be delayed without delaying the entire project.

E

Business

You might also like to view...

Redribbon Gallery reported the following assets on its December 31, 2017 balance sheet

Dec. 31, 2017 Dec. 31, 2016 Cash $35,000 $28,000 Accounts Receivable 97,000 85,000 Merchandise Inventory 80,000 62,000 Prepaid Expenses 29,000 20,000 Property, plant, and equipment, net 30,000 18,000 If the net sales for the year amounted to $850,000, what is the asset turnover ratio for 2017? What will be an ideal response

Business

Which of the following generational groups account for a third of the U.S. population but half of all consumer spending?

A) Millennial B) Generation X C) Generation Z D) baby boomer E) Lost Generation

Business