Create a Gantt chart that shows the WBS.
What will be an ideal response?
Notice that the Microsoft Project Gantt shows non-working days as gaps in the task bars. Since the first day, June 11, is a Monday, days 6 and 7 fall on a weekend and are non-working days. Explain to students that it is possible to design custom calendars that can reflect specials days or hours for a given project.
Computer Science & Information Technology
You might also like to view...
You must start working on the company website (Task 1 ) before you can finish marketing materials (Task 2 ) is an example of the ________ task dependency type in Project 2013
A) Finish-to-Finish B) Start-to-Finish C) Finish-to-Start D) Start-to-Start