What resources have been initially over-allocated in the project described by the table? Assume that all activities will begin at their early start times and require the number of hours per day indicated in the table
Each worker is available for 8 hours per day. Do not level this project. Activity Activity Length Predecessor Resource Resource Hours Per Day A 9 -- Lisa 1 B 8 -- Nathan 7 C 13 A Jake 6 D 11 B Nathan 6 E 6 B Jake 4 F 9 C Lisa 4 G 9 D Jake 5 H 9 E Lisa 6 M 9 F, G Nathan 7 J 4 F, H Lisa 2 K 1 M, J Nathan 6 L 11 K Jake 7