Given the following chart of jobs assigned with Johnson's rule, suppose that all the jobs (A, B, C, etc) could be evenly divided into two tasks (such as A1 and A2, B1 and B2, etc)

Suppose job B is divided into jobs B1 and B2, each with a body work time of 4.5 hours and a paint time of 2 hours. How much is makespan reduced by this splitting of B?

B1 could start on paint at time = 34.5 (1/2 through the completion of B) but E is busy on paint until t = 35, thus B1 will be delayed until t = 35 to start and thus would finish paint at time = 37. B2 could start on paint at time = 39 and would take until t = 41 to finish. Thus makespan is reduced by 2 hours (43 - 41).

Business

You might also like to view...

Jargon has two meanings. One meaning is using familiar words ______________

a. incorrectly b. to describe familiar things c. in unfamiliar ways d. too often

Business

____________ is a process in which top executives regularly review all managers at or above a certain hierarchical level, looking at both performance and potential, and devise developmental plans for their most promising individuals

a. Task planning b. Job planning c. Policy planning d. Process planning e. None of the above

Business