Sketch the Cleland project stakeholder management cycle and discuss the salient elements

What will be an ideal response?

The Cleland Project Stakeholder Management Cycle (below) stresses that all stakeholder management functions are interlocked and repetitive. As time and the project progress, and as investigation work is done, new stakeholders are discovered and must, in turn, be managed. As the environment changes, the project team must cycle through the model again to verify that existing strategies are effective.